Planning for the last phases of the Marshalls Creek Bypass Project – which PennDOT now calls the “Marshalls Creek Traffic Relief Project” – continues. The project was put on hold in April due to funding issues. PennDOT held a public meeting in October to discuss the options for this phase of the project which can be viewed at www.marshallscreekbypass.com/index.cfm
PennDOT posted the following update on January 2, 2009 on its website:
Project Milestones Reached
• PennDOT submitted the Final Traffic Reports to FHWA on November 24, 2008.
• PennDOT submitted the Final EIS (Environmental Impact Statement) Re-Evaluation on November 26, 2008.
• The Kick-Off Meeting for Final Design was held on December 2, 2008.
• A meeting for the Section 106 Programmatic Agreement (environmental/historical compliance agreement) amendment was held on December 4, 2008, with FHWA, SHPO (State Historic Preservation Office), and PennDOT’s District and Central offices.
• The Phase III Archaeology report was delivered to FHWA and PHMC on December 30, 2008.
• A Right-of-Way review meeting was held at the PennDOT District Office on December 30, 2008.
• The Park-and-Ride project bids were reviewed and there is an apparent low bidder (Leeward Construction of Honesdale).
• Core borings have begun and will continue through February 1, 2009.
Upcoming Project Milestones
• The Environmental Review and Permitting will continue to be the challenge when trying to advance the Design/Build contract.
• Rettew Associates is scheduling a preliminary meeting with the permitting agencies for the “bypass” portion of the project.
• The Dewberry Team continues to advance the Final Design.
• The next Bi-Monthly Coordination Meeting is set for January 13, 2009.
• Park-and-Ride lot construction to begin in the spring and last one construction season.